The alignment system provides wall alignment before and after the pour, along with a scaffolding system. The scaffolding provides walkways to install block and a place to pour from.
Set up the alignment and scaffolding system after the wall is 4-6 feet high.
Factors requiring set up prior to reaching 4 to 6 feet include, but are not limited to:
- high or gusty winds
- storms
- exposure
- site layout
Installation and work is commonly from the inside of the structure, however the outside is also an option.
1. Determine placement; inside or outside
2. Calculate placement along wall using the following guidelines:
- Come out 3’ to 4’ from inside of corners
- Calculate 1 brace every 5’ to 6’ linear feet or to OSHA requirements
3. When you get to a window or a door:
- Place alignment on either side 8” to 10” from the bucks
- With larger windows or doors (i.e. garage doors) you may need to calculate alignment in between the bucks
- On short walls, bay windows or close corners; alignment in the middle of the wall is normal
|